林肯高中现代化项目二期

construction phase graphic showing that the school is in the Open phase

Phase II of the 林肯 高中 Modernization project completed in Spring 2023.

项目的照片

监视屋顶上的玻璃窗
Roofing and monitor glass installation continues with water penetration test – Nov. 2021
Adding roof drains and preparing for MDF paneling in the gym - Nov. 2021
Adding roof drains and preparing for MDF paneling in the gym – Nov. 2021
人们穿着安全背心,戴着安全帽看着拆迁
体育馆大堂洗手间2B期拆除工程开始- 11月. 2021
a lift truck in front of a 2-story building that is covered in plastic film
Demolition at the southwest corner of the gym for future elevator and lobby expansion – Dec. 2021
interior demolition down to a dirt and gravel base with pipes sticking up. 墙为混凝土砌块
拆除体育馆大堂洗手间- 12月. 2021
a trench with rebar is seen in the middle of a concrete floor with construction materials around it
Preparing for concrete at the location of the concession stand expansion – Dec. 2021
a two-story L-shaped building has plastic covering the sides where the outside has been removed
拆除未来的电梯扩建- 1月. 2022
墙上有一个篮球圈
健身器材- 1月. 2022
a concrete block wall with a hole from floor to ceiling showing a steel post in the center
Structural steel installed for Performing Arts Center restrooms – Jan. 2022
木质地板健身房的局部视图, 墙下部的保护垫料, 和天窗
体育馆 back in use by school – bleachers and floor refinish summer 2022 – Feb. 2022
an existing wall with a trench below it that has seismic supports installed
Micropiles and grade beam at the auditorium to improve seismic safety – Feb. 2022
一个正在建造的房间,有金属框架和梯子
管道粗加工和健身房大堂洗手间框架- 2月. 2022
a room under construciton with a new steel beam going from floor to ceiling
Structural steel installed in the CTE wing for seismic improvements – Feb. 2022
a large room with white boards on one wall and partial carpet in a curved space
学校重新占用了乐队、唱诗班和管弦乐室. 2022
在一个水泥地板的房间里安装金属框架
更衣室换档位的框架. 2022
一个混凝土平台和墙正在被拆除
Preparation for the elevator expansion for the gym and locker area
在建的建筑物
Upper gym roof completed with space waiting for the elevator expansion – April 2022
一间贴了瓷砖的房间正在被拆除
拆除礼堂洗手间- 2022年4月
后台区域用塑料包裹着墙壁和前部
舞台区域的拆除和危险物品的减少
一个工人正在完成混凝土
2022年4月,通往CTE教室区域的坡道被浇筑
工人们正在把钢架吊到窗户前
在CTE教室中安装支撑框架- 2022年4月
建筑工地内部
Micropile installation complete to improve seismic safety – April 2022
人们在屋顶上操作机器
CTE区域的屋顶更换,2022年5月
正在施工的大房间天花板上的管道工程
2022年5月,在CTE空间安装管道工作
石柱建筑物前面的砖石柱
CTE区域的电梯井壁将于2022年5月完工
砖:部分安装在建筑物外部地面上的砖
东大厅外的砖砌安装,2022年5月
一个有橱柜的在建房间
2022年5月,东大厅的个案工作
一辆混凝土车正在泵送混凝土
2022年5月,在院子里浇筑混凝土工地墙
钢架安装在建筑物的外角
Structural steel installation for the elevator addition – June 2022
每边都有窗户的角落
东体育馆大厅砌石完成售票窗口- 2022年6月
一面铺着红瓷砖的墙,墙上有管子
体育馆地下室安装瓷砖- 2022年6月
一条混凝土走道通向玻璃门
8月西北入口混凝土安装完成. 2022
柜台后面有橱柜和电器
新东方大堂特许摊位- 8月. 2022
一条带有金属梁拱的走道通向一扇门
外部油漆正在进行中- 8月. 2022
红色储物柜,前面有个长凳
安装储物柜长凳- 8月. 2022
红墙房间里的白板和低矮的储物柜
体育馆地下室的白板及可粘墙面
带有金属栏杆的混凝土外墙楼梯
栏杆已安装-九月. 2022
red chairs and stools, and black tall tables sit by a brick building with windows
新庭院家具- 9月. 2022
一个空的奖杯柜,后面有窗户
新的奖杯箱- 9月. 2022
房间里的金属水槽和排水板
厨房设备交付CTE区域- 9月. 2022
树木和低矮的植物在两条混凝土人行道之间的花园里
最终种植过程- 9月. 2022
两堵砖墙,混凝土地板上有切口
Layout and preparations for new wheelchair lift in the auditorium – Sept. 2023
混凝土花盆:混凝土垫中的混凝土花盆
庭院种植橙莎草生物保墒播种机- 10月. 2022
一些小植物被砖墙旁边的混凝土围起来
礼堂西北角景观植物- 10月. 2022
a large room with three stoves with counters between them and metal wall racks behind them
Appliances installed in Career and Technical Education food and nutrition lab – Oct. 2022
在建阳台下面的金属框架
礼堂框架工作- 10月. 2022
凸起的框架用金属固定地板
Corrugated metal decking installed on west mezzanine in auditorium – Oct. 2022
正在施工的房间里的工人
Installing corrugated metal decking, west entrance vestibule of auditorium – Oct. 2022
沿着天花板和下面的金属框架
在大礼堂搭建舞台舞台墙-十一月. 2022
墙壁框架在一个大空间与折叠座椅
礼堂北半径墙的框架- 11月. 2022
模糊的横梁和金属框架的天花板
Framing the ceiling beneath the east mezzanine in the auditorium – Nov. 2022
餐墙和天花板框架与木材上方的天花板框架
西夹层下方的天花板框架- 11月. 2022
混凝土楼梯通向一个未完成的空间
Concrete steps and wall and ceiling framing at the auditorium west entrance vestibule – Nov. 2022
一个大的开放空间有索具网格,上面有灯
礼堂舞台索具安装- 12月. 2022
a black metal spiral staircase goes from the floor level to raised area under construction
Installing the spiral staircase for the west mezzanine in the auditorium – Dec. 2022
a stage area under construction with an opening out to theater seats
View from the stage to the audience with wallboard work in progress – Dec. 2022
木框架里的钢筋在墙边倾斜. 剧院的座位在建筑的旁边
Installing rebar reinforcement in the formwork for the auditorium ramp – Dec. 2022
a concrete floor behind theater seats has a short wall on three sides with a grid inside
安装礼堂无障碍座位区- 12月. 2022
白色瓷砖墙,左边有三个厕所隔间
Installing ceramic tile and toilet stall partitions in north auditorium restroom – Dec. 2022
大空间有部分安装的地板
礼堂舞台地板安装正在进行中. 2023
施工区域在一个黑色的房间与螺旋楼梯
Spiral stairs and handrail intalled on west mezzanine in the auditorium – Jan. 2023
正在建造的小房间
礼堂场景车间灯具安装- 1月. 2023
混凝土舱壁上的金属扶手
礼堂内可达斜坡安装扶手- 1月. 2023
an auditorium with theatre seats with construction workers on the stage
粉刷礼堂天花板,安装扩音器. 2023
a mobility lift is shown next to a short set of six stairs with black walls around both
礼堂西侧前厅安装升降梯
a grid of rigging hardware is shown above a stage with a view of the auditorium audience area
安装在舞台上方的索具硬件- 2月. 2023
a large room with theatre style seating in three sections and a carpeted floor
礼堂座位区铺地毯- 2月. 2023
黑色的地板上有黑色的墙壁,上面有剧院的灯光
舞台绘画完成- 2月. 2023
a group of people look at commercial size stainless steel cooking equpiment
CTE食品与营养实验室设备培训- 2月. 2023
a covered walkway has workers on ladders while painting fence frames
Painting exterior fence frames at east entrance to gym – March 2023
天花板上有灯光的舞台有蓝色的窗帘
舞台幕布安装- 2023年3月
an auditorium with light brown seats looks toward a stage where two people are in the spotlight
主礼堂舞台幕从座位区- 2023年3月
a view out into a auditorium with rows of light colored seats with dark walls, 门, 后墙还有一个控制室
礼堂完工——从舞台上看——2023年3月
three people stand in a control booth with computers - a window looks out to auditorium seating below
剧院灯光控制培训- 2023年3月
an auditorium view from the front with tiered rows of theater seats
从舞台上看已完工的礼堂——2023年4月
a view from behind theater seating toward a stage with a white curtain being installed at the the top
在舞台上重新安装Cyclorama - 2023年4月

项目简介

This project is the second part of the 林肯 高中 modernization project. It included voluntary seismic improvements to the east buildings on the campus, added in 1959. It also included improvements to the gymnasium, performing arts center/auditorium, and Career & 技术教育教室.

林肯现代化的第一部分 was completed in 2019, allowing the school to open as a new attendance area high school in Fall 2019.

体育馆 

  • 自愿抗震升级
  • ada兼容的可访问性升级
  • 更衣室装修
  • 屋顶替换

礼堂,表演艺术中心和CTE

  • 自愿抗震升级
  • ada兼容的可访问性升级
  • 内部升级
  • 屋顶替换

设计 建筑事务所:Mahlum Architects

建设 : Lydig施工

施工管理: 世邦魏理仕股份有限公司.

项目预算: $29.0M

资金来源: Funded by the Building Excellence V (BEX V) Capital Levy, approved by Seattle voters in 2019.